3645.1: Procedures - Change Orders

The following procedures shall be followed with respect to the administration of Board-approved construction, renovation, and remodeling of capital improvements of the District (hereinafter referred to as "construction").

I. Definitions

For purposes of this Rule, the following definition shall apply:

A. "Time is of the Essence" shall mean that time is a material condition in a construction contract and delay in the performance of the contract could disrupt the orderly progress of the construction, affect the operations of the District, or affect the cost of construction.

II. Incorporation of Rule Into Contracts and Agreements

All contracts or agreements between the District and the construction manager(s), architect(s), engineer(s), or consultant(s) shall incorporate this Rule.

III. Change Orders Changing Cost of Construction $25,000 or Less:

A. Change Orders either increasing or decreasing the contract amount by $25,000 or less may be approved by the Superintendent or his/her designee.

B. The Change Order shall not require prior approval of the Ïã¸ÛÁùºÏ²Ê¿ª½±½á¹û but shall be reported to the Ïã¸ÛÁùºÏ²Ê¿ª½±½á¹û at one of its regularly scheduled meetings or special meetings within ninety days of such approval or, in the case of summer projects, by the October Board meeting following the completion of the summer project.

IV. Change Orders Increasing or Decreasing the Cost of Construction in an Amount Exceeding $25,000:

A. Where Time Is of the Essence: Where time is of the essence, proposed Change Orders may be approved by the Superintendent or his/her designee without prior presentation to the Ïã¸ÛÁùºÏ²Ê¿ª½±½á¹û if:

1. The Superintendent or his/her designee determines that time is of the essence and that the decision on the Change Order cannot reasonably be delayed for submission to and consideration by the Ïã¸ÛÁùºÏ²Ê¿ª½±½á¹û, and

2. The Superintendent or his/her designee determines that the Change Order is reasonable and necessary, and

3. In the event the Superintendent or his/her designee, is of the opinion that the proposed cost, scope, or effect of the Change Order is not reasonable or beneficial to the district, the contractor may be directed to proceed with the change proposed subject to a determination of cost at a later date.

Change Orders under this subparagraph shall be reported to the Ïã¸ÛÁùºÏ²Ê¿ª½±½á¹û at one of its regularly scheduled or special meetings within ninety days of the approval of the Change Order by the Superintendent or his/her designee or, in the case of summer projects, by the October Board meeting following the completion of the summer project.

B. Where Time is Not of the Essence:

Change Orders where time is not of the essence shall be submitted to the Ïã¸ÛÁùºÏ²Ê¿ª½±½á¹û for consideration, approval, or rejection at a regularly scheduled or special meeting of the Ïã¸ÛÁùºÏ²Ê¿ª½±½á¹û.

V. Material Changes:

Notwithstanding any other provisions of this Rule, no Change Order may be approved which materially changes the scope of a construction project without prior approval of the Ïã¸ÛÁùºÏ²Ê¿ª½±½á¹û.

VI. Execution of Documents:

Change Order documents may be executed by the Superintendent or his/her designee, and, the Chief Financial Officer is designated to so act on behalf of the Superintendent.
 

Date of Adoption
May 18, 1998
Date of Revision
October 18, 2004
September 17, 2018
July 7, 2025
Reaffirmed
May 3, 2010